Shed building
Cladding quantity estimator
Turns wall dimensions into a board count, working from the cover width after overlap rather than the width on the price list — which is the difference that leaves people 20% short.
The question this answers: “How many boards do I actually order to clad this, and why did the last lot come up short?”
Result
- Boards to order
- 87
- 78.6 to cover the area, rounded up after a 10% allowance.
- Area to clad
- 28.3 m²
- 30.8 m² of wall less 2.5 m² of openings.
- Linear metres
- 313.2 m
- What a yard pricing by the metre will quote against.
- Material cost
- —
- Enter a board price to cost the order.
Worth knowing about this answer
- An ordering estimate, not a specification. It says nothing about whether the structure is adequate, what fixings to use, or whether the building is permitted — those are on the page, and a wall that is cheap to clad can still be one you are not allowed to build.
- Cover width is the exposed face after overlap, not the width printed on the price list. Ordering against nominal width is the standard way to finish a wall short, which is why this tool asks for the harder number.
Show the working
- Gross wall area
14 m perimeter × 2.2 m high30.8 m² - Less openings
30.8 − 2.528.3 m² - Area one board covers
3.6 m × 100 mm cover0.36 m² - Boards before waste
28.3 ÷ 0.3678.61 - Plus waste, rounded up
78.61 × 1.187 boards
Boards to order: 87. Area to clad: 28.3 m². Linear metres: 313.2 m. Material cost: —
Wall area is the perimeter multiplied by the height, less the area of openings. Each board covers its length multiplied by its cover width — the exposed face after overlap, converted from millimetres to metres. Dividing the net area by the area one board covers gives a board count, which is then increased by the waste allowance you chose and rounded up to a whole board.
- Rectangular walls of uniform height. A gable end is entered as its own area rather than by perimeter and height.
- Cover width is constant, which holds for shiplap and for feather edge set to a marked gauge and not for boards lapped by eye.
- The waste allowance is the reader’s judgement and is an input for exactly that reason.
- An ordering estimate and nothing else. It makes no claim about whether the structure is adequate, what fixings to use, what battens or membrane are needed, or whether the building is permitted — the last of those is on the shed building page, where the permitted development limits are quoted at their exact figures.
- Cutting waste around many openings exceeds a flat percentage. A wall that is mostly window generates far more offcut than a plain one, and the tool warns rather than modelling it.
- Nothing about the roof, which is a different covering, a different unit and a different calculation.
Runs entirely in your browser — nothing you type is sent anywhere. Last reviewed 2026-08-17. More on Shed building.